Operational Projects

Leon Solar Park
Leon Solar Park is a 257 MWdc solar project located in Leon County, Texas, within the ERCOT North Hub, strategically positioned between Houston and Dallas. Developed and de-risked by Misae Investments, the project achieved Ready-to-Build (RTB) status in 2023 and was sold to one of the largest infrastructure and energy companies in the world.
The project has a production potential of over 500,000 MWh in its first year alone, and an estimated 19.9 million MWh over its 40-year lifetime.
Location
Leon County, Texas
Power Capacity
257 MWdc
Commercial Operation Date
July 2026
Investor
Ferrovial
Interconnection
Oncor 138 kV substation
CO₂ Offset
183,000 tons/year
(equivalent to powering 49,900 homes)
Childress Solar Park
Childress Solar Park marked the first utility-scale solar farm in Childress County, the Panhandle, and one of the largest single-site solar projects in ERCOT at the time. Developed by Misae Investments, the 320 MWdc project sold in 2018 to Copenhagen Infrastructure Partners (CIP) and reached Commercial Operation (COD) in 2020.
This project established Childress County as a new clean energy hub, opening the door for future large-scale solar and data-center investments.
Location
Childress County, Texas (ERCOT West Hub)
Power Capacity
320 MWdc
Commercial Operation Date
March 2020 COD
Investor
CIP and IKEA
Interconnection
Tesla’s substation, Childress County
CO₂ Offset
~201,000 tons/year
(equivalent to powering 55,600 homes)

Misae Solar Park II
Located in Childress, Texas, Misae Solar Park II is next to the successfully developed 324 MW/dc Phase I that was sold in 2018 to Copenhagen Infrastructure Partners (CIP), a major infrastructure fund with an established track record in the US renewables market.
At 517 MWac/692 MWdc, the project is one of the largest solar investment opportunities in the US.
Location
Childress County, Texas (ERCOT West Hub)
Power Capacity
692 MWdc
Commercial Operation Date
August 2025 COD
Investor
Greenalia
Interconnection
Fagus substation, Childress County
CO₂ Offset
~826,000 tons/year
(equivalent to powering ~130,000 homes)