LEON SOLAR PARK (730 MWh)
Developed by Misae Investments · Sold in 2023
TIMELINE PATH TO COD
November 2023
Ready to Build
February 2024
Engineering LNTP
July 2024
Construction NTP
July 2026
COD

Execution of
Interconnection
Agreement
-
Selection of equipment and initial down payments
-
EPC/BOS contrract negotiation
-
LNTP issued to release design
-
Construccion NTP
-
EPC Managment
-
Bonding
-
Subcontracting
-
Project to reach full commercial operation in July 2026
LAYOUT

Power:
210 MWac/287 MWdc
Rated Power:
239.4 MWac
At POI:
210.1 MWac
Installed Power:
287 MWdc